Closeout: punch list, documents, retainage and final payment
Closeout is where the last of your money is — usually retainage plus any unbilled work. Finish the punch list fast and get written sign-off, deliver closeout documents and attic stock with transmittals, bill retainage and your final pay application as soon as you're eligible, and exchange final lien waivers only as payment clears. Track the warranty period and any lien or bond deadlines until the last check is in.
By Michael Reddy, IntelBid
After this lesson you can
- Run closeout as a checklist, not a scramble
- Deliver documents and attic stock that satisfy the specs
- Collect retainage and final payment without giving up rights early
What does closeout include?
| Item | What to deliver | Why it matters |
|---|---|---|
| Punch list | Every item completed, with written sign-off | Open punch items are a common reason retainage sits |
| Warranties | Manufacturer warranties and your workmanship warranty, as the specs require | Usually a condition of final payment |
| Maintenance data | Care and cleaning instructions for each product | Required closeout submittal on most projects |
| Attic stock | Extra material per the specs, with a signed transmittal | Proof it was delivered — and to whom |
| Record documents | As-installed information such as seam layouts or product locations, when required | Owner's records for future repairs |
| Final lien waivers | Yours, and your suppliers' when required | The GC needs them to close its own contract |
| Final pay application and retainage billing | Your last bills, with required backup | The remaining money |
In what order should you close out?
- Walk and punch earlyWalk your areas with the GC as soon as you're substantially complete, get the punch list in writing, and finish it quickly.
- Send closeout documents the week you finishWarranties, maintenance data and attic stock transmittals shouldn't wait for someone to ask.
- Bill what's leftSubmit the final pay application for any remaining contract value and approved change orders.
- Bill retainage when eligibleRequest release as soon as the contract's trigger is met — nobody releases money that hasn't been requested. See how retainage works.
- Exchange waivers carefullyConditional final waivers with the final bills; unconditional only after payment clears — see lien waivers.
- Watch your deadlinesLien and payment bond deadlines keep running after you leave the site. Calendar them until you're paid in full.
After the job: warranty and lessons
- Track the warranty period from the date the specs define — often substantial completion — and respond to warranty calls promptly.
- Compare estimate to actual: production, material, change orders and margin. Feed it back into your pricing and bid decisions.
- Ask for a reference from a GC you worked well with — it helps your next prequalification.
What closeout documents does a flooring subcontractor provide?
Typically warranties, maintenance data, attic stock transmittals, any required record documents such as seam layouts, final lien waivers, and the final pay application — as listed in the project specifications.
When should a subcontractor bill retainage?
As soon as the contract's release trigger is met, such as substantial completion or acceptance of your work. Submit a retainage billing rather than waiting for the GC to release it on its own.
When should I sign a final unconditional lien waiver?
Only after final payment, including retainage, has actually cleared. Until then, use a conditional final waiver.
Key points
- Closeout is where retainage and final payment live — run it as a checklist.
- Finish the punch list and send closeout documents without being asked.
- Bill retainage when eligible; sign unconditional waivers only after payment clears.
Closeout on the project
When the work is accepted, Bill retainage on the SOV tab creates the release billing for everything held, alongside your pay applications. Keep warranties, maintenance data and attic stock transmittals in the project's Project Docs, so the closeout package is on the job, not in someone's inbox.
Start your free trialEvery trial starts with a sample project loaded, so you can try this before connecting anything.
Get new lessons, plus $100 toward IntelBid
New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.
About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.