Resilient flooring and tile need a flat substrate, and manufacturers publish the maximum deviation they allow over a given distance — large-format tile and LVT are especially sensitive. Concrete is usually specified and measured differently, with F-numbers under ASTM E1155, so a slab can meet its own spec and still be too rough for your floor. Price a stated amount of prep, state the tolerance it assumes, and put anything beyond it on a unit price.

By Michael Reddy, IntelBid

After this lesson you can

  • Explain the gap between concrete flatness specs and flooring tolerances
  • Recognize the substrate conditions that need preparation
  • Qualify prep so work beyond your allowance is paid

Why can a “flat” slab still be a problem?

Concrete specificationFlooring manufacturer
Typical measureF-numbers (FF for flatness, FL for levelness) per ASTM E1155Maximum deviation over a distance, checked with a straightedge
When it's measuredUsually soon after the slab is placedWhen you're ready to install
What it describesStatistical flatness across the whole floorLocal dips and humps your floor will show

A slab can pass its F-number requirement overall and still have local dips and humps outside the flooring tolerance — and slabs can change after placement as they cure and other trades work on them. That's the gap your qualification has to cover.

What prep conditions should you plan for?

ConditionTypical fixHow to price it
High spots and humpsGrindingUnit price per SF
Low spots and dipsPatching or self-leveling underlaymentIncluded amount plus unit price
Cracks and control jointsFill non-moving cracks; honor moving jointsLF, or included within limits
Curing compounds, sealers, paintRemoval by grinding or chemical methodsExcluded or unit price
Old adhesive residueScraping or grindingUnit price, or in removal scope
Contamination (oil, grease)Cleaning or grindingExcluded or unit price

Sample prep qualification

“Price includes floor preparation limited to patching and skim-coating up to 5% of the floor area and filling of non-moving cracks. Price assumes the substrate is within the flooring manufacturer's published flatness tolerance and is free of curing compounds, sealers, coatings and contaminants. Grinding, self-leveling underlayment beyond areas shown, and removal of compounds, sealers or coatings are excluded and available at the unit prices listed.”

Example to adapt — set your own limits

Inspect before you install

Many specs say that starting installation means you accept the substrate. Before installing in each area, inspect it, and give the GC written notice of unacceptable conditions — with photos and locations — while it's still their problem to fix or pay for.

Installing over a bad floor makes it yours
Once flooring goes down over a substrate you didn't flag, the failure is usually your warranty problem. A short written notice before starting is cheap insurance.
Who is responsible for leveling a floor before flooring installation?

It depends on the contract. Specs often put preparation on the flooring contractor, so state in your proposal how much prep is included and price additional leveling or grinding as unit prices.

What are FF and FL numbers?

F-numbers measured under ASTM E1155 describe concrete floor flatness (FF) and levelness (FL) statistically across a floor. They don't guarantee a slab meets a flooring manufacturer's local flatness tolerance.

Does installing flooring mean accepting the substrate?

Many specifications say so. Inspect each area before installing and give written notice of unacceptable conditions first.

Key points

  • A slab can meet its concrete spec and still fail your flooring tolerance.
  • Include a stated amount of prep; price the rest as unit prices.
  • Inspect and give written notice before installing.
In IntelBid · Proposal builder

Prep that's visible on the proposal

Add floor prep, grinding and self-leveling underlayment as their own lines with units and prices — or as Add alt lines — and state the included amount in a note on the proposal, so what's covered and what costs extra is clear on the proposal the GC levels.

Try it in IntelBid

A 2-minute guided tour on a sample project — nothing touches real data. New to IntelBid? You'll start a free trial first.

IntelBid Learn by email

Get new lessons, plus $100 toward IntelBid

New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.

Email me new IntelBid Learn lessons, IntelBid feature updates and offers such as promo codes. Unsubscribe anytime. See our privacy policy.

About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.

Floor Flatness Tolerance & Floor Prep Qualifications · IntelBid