Submittals and substitutions: pricing what happens after award
Submittals are the product data, samples, drawings and closeout documents the architect reviews before you order or install — the spec's Part 1 lists them. Substitutions are requests to use a product other than the one specified; many projects only consider them before bids are due, through a formal prior-approval request. Both take office time, samples and schedule, so price them during bidding rather than discovering them after award.
By Michael Reddy, IntelBid
After this lesson you can
- List the submittals a flooring spec requires and what each costs
- Build submittal review time into material lead times
- Use substitution requests at the right moment, or price the specified product
What do flooring specs usually ask for?
| Submittal | What it is | Cost to you |
|---|---|---|
| Product data | Manufacturer data sheets for each product, adhesive and accessory | Office time |
| Samples | Physical samples of each color and product, sometimes in multiple sets | Sample costs, shipping, time |
| Shop drawings | Seaming diagrams for sheet goods or broadloom, pattern and layout drawings | Drafting or layout time |
| Test reports | Moisture and pH results, flammability or slip-resistance data | Testing cost if yours, office time |
| Qualification data | Installer certifications and experience | Office time; certification costs |
| Mockup | An installed sample area approved before the main install | Labor and material |
| Closeout submittals | Maintenance data, warranties, attic stock transmittals | Office time; attic stock |
Why submittals affect price and schedule
- You usually can't order until submittals are approved. Review and resubmittal time stacks on top of the manufacturer's lead time.
- Rejected submittals cost twice. A resubmittal is another round of samples and another wait.
- Long lead times meet late approvals. If carpet tile has a long lead time and approval arrives late, your install date slips — or you pay for faster freight.
- Submittal procedures live in Division 01 (often 01 33 00): number of copies, electronic formats, review periods and whether the GC reviews before the architect.
How do substitutions work?
A substitution is a request to use a product other than what's specified — to save cost, shorten a lead time, or use a product your crews install better. When and how you can ask is set by the specs, usually Section 01 25 00 (Substitution Procedures) and the instructions to bidders.
| When | How it usually works | What to do |
|---|---|---|
| Before bids are due | A prior-approval request by a stated deadline; approved products are added by addendum so every bidder can use them | Submit early with data showing the product is equal; don't price it unless it's approved |
| After award | Often limited to products that are unavailable, discontinued or can't meet the schedule | Expect to justify the request and show no cost or schedule harm to the owner |
| “Or approved equal” specs | Equal products may be proposed, but the architect decides | Price the specified product unless approval is in writing |
Budget the paperwork
On a small job, submittals may be an afternoon. On a large multi-product job with samples, mockups and seaming diagrams, they can be days of office time plus material. Either recover them in your overhead or, for heavy jobs, price them as part of the job — just don't leave them out.
What are submittals in construction?
Documents and samples a contractor provides for the architect's review before ordering or installing: product data, samples, shop drawings, test reports, qualifications, and closeout documents such as warranties and maintenance data.
What is a prior approval substitution request?
A request made before bids are due asking to use a product other than the one specified. Approved products are usually added by addendum so all bidders can price them.
Can I substitute flooring products after award?
Sometimes, but many specs limit post-award substitutions to unavailable or discontinued products or schedule problems, and require you to show the substitute is equal at no extra cost to the owner.
Key points
- Submittals take time, samples and money — price them.
- Material lead times start when submittals are approved, not when you win.
- Offer unapproved substitutes as voluntary alternates, never as your base bid.
Submittals tracked on the job
Once a job is won, submittal correspondence in IntelBid is logged against the project under its own Submittal category, so the history of what was sent, returned and resubmitted stays with the job rather than scattered across inboxes.
Start your free trialEvery trial starts with a sample project loaded, so you can try this before connecting anything.
Get new lessons, plus $100 toward IntelBid
New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.
About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.