Reading flooring specifications: what to pull from Parts 1, 2 and 3
Flooring spec sections follow a three-part format. Part 1 (General) sets submittals, quality requirements, extra materials, warranty and delivery rules. Part 2 (Products) names the acceptable manufacturers, products and substitution rules. Part 3 (Execution) covers substrate testing and preparation, installation and protection. Most of the money is in Part 1's extra-materials and warranty lines and Part 3's testing and preparation requirements.
By Michael Reddy, IntelBid
After this lesson you can
- Navigate any flooring spec section using the three-part format
- Pull the requirements that affect price from each part
- Spot proprietary specs and substitution rules before you price
Where flooring lives in the project manual is covered in bid packages and addenda. This lesson is what to read once you've found the section.
What does each part of a spec section cover?
| Part | Typical articles | What to pull out |
|---|---|---|
| Part 1 — General | Summary, related sections, submittals, quality assurance, mockups, delivery and storage, field conditions, warranty, extra materials | Submittal list, installer qualifications, mockups, acclimation and site conditions, warranty length, attic stock quantities |
| Part 2 — Products | Manufacturers, products, performance requirements, accessories, adhesives, substitutions | Basis-of-design product, acceptable equals, required accessories and adhesives, whether substitutions are allowed |
| Part 3 — Execution | Examination, preparation, installation, cleaning, protection | Moisture and pH testing, substrate preparation and flatness, installation method and pattern, protection until turnover |
- 1.1 Summary and related sections
- 1.2 Submittals: product data, samples$
- 1.3 Quality assurance: installer qualifications, mockup$
- 1.4 Delivery, storage and field conditions: acclimation, temperature$
- 1.5 Warranty$
- 1.6 Extra materials: attic stock$
- 2.1 Manufacturers: basis of design and acceptable equals
- 2.2 Resilient tile flooring
- 2.3 Adhesives, primers and accessories$
- 3.1 Examination
- 3.2 Preparation: moisture and pH testing, flatness$$
- 3.3 Installation
- 3.4 Cleaning and protection until turnover$
Part 1: where the hidden costs sit
- Submittals — product data, samples, seaming diagrams for sheet goods or broadloom, maintenance data and warranties. Each costs office time; physical samples cost money. More in submittals and substitutions.
- Quality assurance — installer certification by the manufacturer, years of experience, a required mockup. A mockup is real labor and material; price it.
- Extra materials (sometimes “maintenance material submittals”) — the attic stock you must hand over, usually as a percentage of installed quantity or a number of cartons per product. It belongs on its own line, not inside waste.
- Field conditions — required temperature and humidity before, during and after installation, and acclimation periods. If the building won't have permanent HVAC running when you install, that's a schedule and cost risk to qualify.
- Warranty — the manufacturer's warranty is usually automatic; an installer's workmanship warranty of more than one year is a cost you're carrying.
Part 2: products, equals and substitutions
- Basis of design — the product the designer based the spec on. Other manufacturers may be listed as acceptable if they meet the basis-of-design criteria.
- “Or approved equal” — you may propose another product, but approval isn't guaranteed. Price the specified product unless you've been told otherwise.
- Proprietary or sole-source specs — one product, no substitutions. You lose the ability to shop material pricing, so get your distributor quote early.
- Accessories and adhesives — specified adhesives, primers, transition strips and edge trims are easy to miss and add up.
Part 3: testing, preparation and installation
Part 3 is where flooring bids lose money. Read it line by line:
- Moisture testing — commonly relative-humidity testing per ASTM F2170 or calcium chloride testing per ASTM F1869, plus pH testing. Who performs and pays for the tests, and what happens when results exceed the limit, is what you need to know.
- Acceptable limits — the maximum moisture and pH readings usually come from the flooring or adhesive manufacturer. Above them, mitigation is required — find out whose scope that is.
- Preparation and flatness — required flatness tolerance, patching, grinding, crack treatment and self-leveling underlayment. If the spec makes you responsible for bringing any slab into tolerance, that's unlimited scope without a stated assumption.
- Installation — installation method, pattern (quarter-turn, ashlar, herringbone) and seam placement, which drive waste and labor.
- Protection and cleaning — protecting finished floors from other trades until turnover, and final cleaning or finish application.
How to turn these risks into qualifications and exclusions is covered in Module 7; how to quantify the prep work is in floor prep and moisture takeoff.
What is the three-part specification format?
A standard structure for spec sections: Part 1 General (administrative and quality requirements), Part 2 Products (materials and manufacturers) and Part 3 Execution (preparation, installation and protection).
What does “basis of design” mean in a specification?
It's the specific product the designer used to write the spec. Other listed or approved products must match its performance and appearance criteria.
Where is attic stock specified?
Usually in Part 1 of the flooring section under extra materials or maintenance material submittals, stated as a percentage of installed quantity or a number of units per product.
Key points
- Part 1 holds submittals, mockups, attic stock and warranty — all cost money.
- Part 2 tells you whether you can shop the product or must buy one brand.
- Part 3's testing and preparation language is where flooring bids lose money.
Specs next to your takeoff
Upload the flooring spec sections to the bid with a SPEC_ file-name prefix. When Auto Draft builds a proposal from your takeoff, it reads those spec files alongside it, and your qualifications and exclusions come from your own scope library rather than from the last proposal someone could find.
Start your free trialEvery trial starts with a sample project loaded, so you can try this before connecting anything.
Get new lessons, plus $100 toward IntelBid
New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.
About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.