Taking off floor prep, moisture testing and demolition

Quantify floor prep as its own lines, not a hopeful per-SF add. Count moisture tests from the test standard (ASTM F2170 and F1869 both call for three tests in the first 1,000 SF plus one per additional 1,000 SF). Estimate patching and grinding by area, self-leveling underlayment by volume at an assumed depth, and demolition by area and existing material. Where the real condition is unknown, price an assumption and offer unit prices for the rest.

By Michael Reddy, IntelBid

After this lesson you can

  • Calculate the number of moisture tests a slab requires
  • Estimate self-leveling underlayment from area and depth
  • Structure prep and demolition as quantities, assumptions and unit prices

The flooring takeoff guide explains why prep and moisture are where flooring bids lose money. This lesson is how to put numbers on them.

How many moisture tests does a slab need?

If the spec puts testing on you, the count comes from the test standard. ASTM F2170 (in-situ relative humidity) and ASTM F1869 (calcium chloride) both call for three tests in the first 1,000 SF, plus one for each additional 1,000 SF. Check the edition the spec references and any additional locations it requires.

Moisture test count for an 18,000 SF slabWorked example · illustrative numbers
Slab area to receive flooring
18,000 SF
Test method
ASTM F2170 relative humidity
  1. First 1,000 SF: 3 tests.
  2. Remaining area: 18,000 − 1,000 = 17,000 SF → 17 more tests, one per 1,000 SF.
  3. Total: 3 + 17 = 20 tests.
Price 20 tests, plus a return trip if the slab isn't ready when you first test. If an independent agency tests instead, carry nothing — and say so in your proposal.

Patching, grinding and self-leveler

Prep itemTake off asNotes
Crack repairLFOnly cracks that telegraph or move; check the spec's crack treatment
Patching and skim coatingSFOften an allowance or unit price until the slab is seen
Grinding high spots, removing coatingsSFCuring compounds and sealers may need to come off before adhesive
Self-leveling underlaymentSF at an assumed depth → volume → bagsDepth is the big unknown — state it
Moisture mitigation systemSFFrequently priced as an alternate or unit price above a stated reading
Self-leveling underlayment by volumeWorked example · illustrative numbers
Area needing leveler
3,000 SF
Assumed average depth
1/4 inch
Yield per bag (example — use the product data)
0.45 cu ft
Waste and overpour allowance
10%
  1. Depth in feet: 0.25 ÷ 12 = 0.0208 ft.
  2. Volume: 3,000 × 0.0208 = 62.5 cu ft.
  3. Bags: 62.5 ÷ 0.45 = 138.9 → 139 bags.
  4. With 10% allowance: 139 × 1.10 = 152.9 → 153 bags, plus primer per the manufacturer.
At an assumed 1/4 inch, 153 bags. Doubling the real depth to 1/2 inch doubles the material — which is why the depth assumption must be written into your proposal.

Removing existing flooring

  • Take off removal by area and existing material — carpet, carpet tile, VCT, sheet vinyl and ceramic tile remove at very different speeds.
  • Separate adhesive removal — scraping or grinding residue so the new floor bonds is its own operation.
  • Count base removal in LF if old base comes out.
  • Include disposal — dumpsters, hauling and landfill fees.
  • Never assume hazardous material is someone else's scope without saying so. Older flooring and cutback adhesives may contain asbestos; testing and abatement need a clear written exclusion.

When you can't see the slab: assumptions plus unit prices

You often bid prep before the building exists, or before existing flooring is removed. Price a stated assumption in your base bid, and offer unit prices for anything beyond it:

“Base bid includes patching up to 5% of the floor area and self-leveling underlayment at an average of 1/8 inch in areas shown. Additional preparation at $X per SF. Moisture mitigation, if required above the manufacturer's limit, at $Y per SF.”

How to write those assumptions so they hold up is Module 7; how unit prices work is covered in alternates, unit prices and allowances.

How many moisture tests are required per square foot of concrete?

Under ASTM F2170 and ASTM F1869, three tests for the first 1,000 SF and one for each additional 1,000 SF. Always check the edition and any extra locations the project specification requires.

How do you estimate self-leveling underlayment?

Multiply the area by the average depth in feet to get cubic feet, divide by the bag yield from the manufacturer's data, round up, and add a small allowance for waste and overpour. State the depth you assumed.

How should flooring contractors price unknown floor prep?

Include a stated amount of prep in the base bid and offer unit prices per square foot for additional preparation and moisture mitigation, so unknown conditions become measured changes instead of absorbed costs.

Key points

  • Moisture test counts come from the standard: 3 for the first 1,000 SF, 1 per 1,000 SF after.
  • Self-leveler is volume: area × depth ÷ bag yield — and the depth is an assumption to state.
  • Price a written prep assumption plus unit prices for everything beyond it.
In IntelBid · Proposal builder and scope library

Prep as priced lines and standard exclusions

In IntelBid, prep, testing and removal go on the proposal as their own lines with their own units and prices, and your standard prep assumptions and hazardous-material exclusions come from your scope library — so every proposal carries the same protection, not whatever the last one said.

Start your free trial

Every trial starts with a sample project loaded, so you can try this before connecting anything.

IntelBid Learn by email

Get new lessons, plus $100 toward IntelBid

New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.

Email me new IntelBid Learn lessons, IntelBid feature updates and offers such as promo codes. Unsubscribe anytime. See our privacy policy.

End of Module 4Take the Module 4 quiz · 5 questions