Pricing one project for several GCs
When several GCs invite you to the same project, start from one takeoff and one cost estimate, then adjust each GC's proposal only for differences that are real: the scope that GC's bid form assigns to flooring, its subcontract terms and payment history, the alternates it asks for, and your read on who will win. Keep every GC's number confidential, and track exactly which version went to whom.
By Michael Reddy, IntelBid
After this lesson you can
- Build every GC's proposal from one estimate
- Decide which differences justify a different price
- Keep versions straight and each GC's number confidential
Start from one estimate
The drawings are the same for every GC, so the takeoff and the cost build should be too. Differences between GCs are adjustments on top of that one estimate — which means when an addendum lands, you re-price once and every GC's proposal follows. The basics of why one project reaches you several times are in how commercial bidding works.
Which differences justify a different price?
| Difference | Example | How to adjust |
|---|---|---|
| Scope split | GC A puts base and prep in flooring; GC B carries base with another trade | Different scope, different price — and different inclusions |
| Alternates and unit prices | Only one GC's bid form asks for a moisture mitigation alternate | Price only what each form asks for |
| Subcontract terms | Higher retainage, pay-if-paid, or a long payment cycle | Price the cost of carrying the money — see pay-if-paid |
| Payment history | One GC pays in 30 days, another in 90 | Carry more for slow payers |
| Relationship and odds | A GC that awards fairly and repeats work vs. one that shops numbers | Sharpen for the first; hold firm for the second |
| Schedule and phasing | Different proposed schedules or phasing plans | Mobilizations and labor productivity change |
- Base price from your estimate
- $97,145
- GC A
- Wants floor prep allowance included (+$2,400)
- GC B
- Wall base by another trade (−$6,300); pays in about 90 days
- Carrying cost for slow pay (your choice)
- 2%
- GC A: $97,145 + $2,400 = $99,545.
- GC B scope: $97,145 − $6,300 = $90,845.
- GC B carrying cost: $90,845 × 2% = $1,816.90 → $92,662.
Keep the versions straight
- Name every file by GC and versionA proposal file should say which job, which GC and which version it is — no “final_final_v2.pdf”.
- Log what went whereFor each GC: the version, the total, the date and time sent, and who received it.
- Re-send to everyone after an addendumWhen a change affects the price, update every GC still bidding — not just the first one who asks.
- Note what you learnIf a GC tells you they carried your number, or who won, record it against that GC's bid.
Should a subcontractor give every GC the same price?
Not necessarily. Prices can legitimately differ when scope splits, alternates, subcontract terms, payment history or schedules differ between GCs. What must stay the same is honesty and confidentiality.
Is it bid shopping to give GCs different prices?
No. Bid shopping is sharing one party's price with competitors to drive prices down. Pricing each GC's actual scope and terms is normal estimating.
How do you track proposals sent to multiple GCs?
Keep one estimate for the project and a record per GC of the proposal version, total, date sent and recipient, and update every GC still bidding when an addendum changes the price.
Key points
- One takeoff and cost estimate; per-GC adjustments on top.
- Only real differences in scope, terms, history or schedule change the price.
- Separate emails, clear file names, and a log of what went to whom.
One bid, a proposal per GC
In IntelBid every GC invited to a project sits on the same bid. Build the lines once, adjust a GC's version where its scope differs, and generate a separate proposal and email draft for each GC — using the scope calculator to price any line from crew days and material cost.
Try it in IntelBidA 2-minute guided tour on a sample project — nothing touches real data. New to IntelBid? You'll start a free trial first.
Get new lessons, plus $100 toward IntelBid
New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.
About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.