Writing inclusions, exclusions and qualifications that hold up
Inclusions say exactly what your price covers, exclusions say what it doesn't, and qualifications (or clarifications) state the assumptions the price depends on. Write them specifically — naming spec sections, product codes, quantities, conditions and who is responsible — so a GC can level your number and a dispute after award has a written answer. Vague lines like “standard exclusions apply” protect nobody.
By Michael Reddy, IntelBid
After this lesson you can
- Write inclusions tied to spec sections and finish codes
- Build an exclusions list that covers flooring's common risks
- Phrase assumptions so changed conditions become change orders
What's the difference between the three?
| Section | What it does | Example |
|---|---|---|
| Inclusions | Defines what your price covers | “Carpet tile CPT-1 and LVT-1/LVT-2 per the finish schedule, 4-inch rubber base RB-1, transitions at material changes, and attic stock per Section 09 68 13.” |
| Exclusions | Defines what your price does not cover | “Moisture mitigation, testing or abatement of hazardous materials, and furniture moving.” |
| Qualifications | States the assumptions and conditions behind the price | “Price assumes normal working hours, Monday through Friday, and three mobilizations.” |
What makes a line hold up?
- Specific, not generic. “Floor prep beyond patching up to 5% of floor area” holds up; “floor prep by others” invites an argument about what prep means.
- Tied to the documents. Name spec sections, finish codes, sheet numbers and the addenda your price includes.
- Limited by a number. Mobilizations, patching percentage, working hours, submittal review time — numbers turn a disagreement into a count.
- Clear about who does it. When you know the responsible party, say so: “furniture moving by owner,” “temporary HVAC by GC.”
- Consistent with your price. Never exclude something you actually priced, and never include something you didn't.
A starter exclusions list for flooring
| Risk | Example exclusion or qualification | Lesson |
|---|---|---|
| Concrete moisture | Mitigation above manufacturer limits excluded; unit price offered | Moisture qualifications |
| Floor flatness and prep | Prep limited to a stated amount; grinding and leveler beyond it at unit prices | Flatness and prep |
| Hazardous materials | Testing, abatement and disposal excluded | Existing conditions |
| Existing flooring | Removal limited to one layer of a stated material | Existing conditions |
| Furniture and equipment | Moving, disconnecting and reconnecting by owner | Existing conditions |
| Building conditions | Permanent or temporary HVAC, lighting and power by others before installation | Flooring specifications |
| Schedule | Normal hours; stated number of mobilizations; premium time as a change | Mobilization and site conditions |
| Protection | Protection after turnover and damage by other trades excluded | Existing conditions |
| Bonds, permits, tax | Bond cost excluded unless requested; state whether sales tax is included | Material, freight and tax |
How do GCs read your qualifications?
During bid leveling, a GC estimator adds a plug number for every exclusion that a competitor included. A long list of exclusions for normal scope makes your leveled number go up. The balance: exclude the risks that are genuinely unknowable or not yours, and price the ordinary scope a competent flooring contractor is expected to carry.
What is the difference between an exclusion and a qualification?
An exclusion names work your price doesn't cover. A qualification, or clarification, states an assumption your price depends on, such as working hours, number of mobilizations or a substrate condition.
What should a flooring subcontractor exclude?
Commonly moisture mitigation above manufacturer limits, floor prep beyond a stated amount, hazardous material testing and abatement, furniture moving, temporary building conditions, protection after turnover and premium-time work — adjusted to what the documents require and what you actually priced.
Do exclusions on a proposal apply after award?
Only if they become part of the contract. A GC's subcontract usually replaces proposal terms, so ask for your proposal or its exclusions to be attached or referenced before signing.
Key points
- Inclusions define the price, exclusions limit it, qualifications state its assumptions.
- Specific, document-tied, numbered lines hold up; generic ones don't.
- Make sure your exclusions end up in the signed subcontract.
Inclusions and exclusions on every document
Your standard inclusions and exclusions are set once in Settings → Documents and print on every proposal. Each proposal and change order also has Notes for this job's qualifications — a moisture limit, a plan-set date, the prep your price includes — printed right above those lists, so your qualifications travel with every number you send.
Try it in IntelBidA 2-minute guided tour on a sample project — nothing touches real data. New to IntelBid? You'll start a free trial first.
Get new lessons, plus $100 toward IntelBid
New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.
About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.