Proposal versions and revisions: changing a price without confusion
Once a proposal has been sent, never quietly change it — issue a new version. Give every revision a version number and date, say exactly what changed and why (an addendum, a scope clarification, a price update), and send it to every GC still bidding that had the old one. Keep the versions you sent untouched as your record of what each GC was offered.
By Michael Reddy, IntelBid
After this lesson you can
- Recognize when a proposal needs a new version
- Write a revision that makes the change obvious
- Handle a mistake found after bid day the right way
When do you need a new version?
| Trigger | Example |
|---|---|
| An addendum changes scope | Addendum 3 adds 1,200 SF of LVT to a corridor |
| A GC clarifies its scope or bid form | The GC confirms wall base belongs in flooring |
| An alternate is added or changed | The owner asks for a new deduct alternate |
| Your price validity runs out | Award comes after 60 days and material pricing moved |
| Negotiation after scope review | Value engineering swaps a product |
| You find an error | A room was missed in the takeoff |
What must a revision say?
- Version number and date — “Version 3, June 12.”
- Why it changed — “Revised per Addendum 3,” or “Revised per scope review with ABC Builders.”
- What changed — the lines and totals that moved, with the old and new amounts.
- Current basis of bid — every addendum now included.
- What it replaces — “This proposal supersedes Version 2 dated June 3.”
- Version 2 base bid
- $97,145
- Addendum 3 adds
- 1,200 SF of LVT
- Your installed sell rate for that LVT
- $6.10 / SF
- New transitions created
- $180
- Added LVT: 1,200 × $6.10 = $7,320.
- Plus new transitions: $7,320 + $180 = $7,500.
- Version 3 base bid: $97,145 + $7,500 = $104,645.
Can you change your bid after bid day?
Before a GC relies on your number, a correction is usually just a new version. After bid day it gets harder. On private work, a GC may accept a revision — or may not. On public work, bids to the owner often can't be withdrawn after opening except under specific rules for clerical mistakes. And in some states, a GC that relied on your price to build its own bid can hold you to it; California's Drennan v. Star Paving decision is the well-known example.
Keep the history
- Never overwrite a version you sent. It's your record of what the GC was offered.
- Keep every sent PDF, with the date and the recipient.
- Make the subcontract reference the final version by number and date, so your qualifications come with it.
How do you revise a bid proposal?
Issue a new version with a number and date, state what changed and why, list the addenda now included, say which version it supersedes, and send it to every GC that had the previous version.
Can a subcontractor change a bid after submitting it?
Often yes before the GC relies on it, but after bid day it depends on the GC and the project. Public bids may have strict withdrawal rules, and in some states a GC that relied on a subcontractor's price can hold the subcontractor to it.
Should I resend my proposal after an addendum?
Yes, if the addendum affects your scope or price — or confirm in writing that it doesn't. Send the revision to every GC still bidding.
Key points
- A sent proposal never changes — a new version does.
- Every revision says what changed, why, and what it replaces.
- Report mistakes immediately and in writing.
Versions that protect what you sent
Each time you generate a proposal, IntelBid lets you overwrite the current version or create a new one. A version that's been marked sent is never overwritten — generating again creates the next version, so what each GC actually received stays on record.
Try it in IntelBidA 2-minute guided tour on a sample project — nothing touches real data. New to IntelBid? You'll start a free trial first.
Get new lessons, plus $100 toward IntelBid
New modules as they're published. Confirm your email and we'll send a $100 credit toward your IntelBid membership.
About the author. Michael Reddy builds IntelBid, bid management software for commercial flooring subcontractors. These lessons come from the bid desk: how the work is priced, won and paid for.